| System | |||||||
| The choice of system will be based on the requirements - i.e height, spans, fire resistance thermal shield, acoustics and other loading factors. | |||||||
| Components | |||||||
| StrandecTM - SSP - slab planks with
a Tongue and Groove edgeson the long sides and square edges on the short
side • SSP(N) - Strandec slab plank natural • SSP(C) - Strandec slab plank thermal • Thickness 30, 40 and 50mm • Width 600mm • Length 1200mm • Panel clips • Rebars as per design requirements • Glassfibre Mat as a substrate for finishing plaster where required • Finishing plaster if required |
|||||||
| System Choices | |||||||
| StrandecTM Panel made from Inorganic
Bonded Composites completely mineralized using Portland cement makes it
as strong as wood, which does not shatter, or crack and is fire resistant.
The matrix structure gives it strength with lightweight and also with unique
acoustical and thermal insulating. The definitive properties of StrandecTM combined with the established strengths of concrete a wide range of composite slabs can be assembled in a fast track construction StrandecTM Composite Slabs form to varying fire ratings, acoustics, and thermal performance requirements. |
|||||||
| Applications | |||||||
| StrandecTM Composite Slabs can be an ideal choice for various end users such as offices, schools, hotels, hospitals, industries, theatres, multiplexes, multi level parking lots etc. | |||||||
![]() |
|||||||
| Construction Procedures | |||||||
| Plank placement - StrandecTM Slab planks shall
be installed on available structural columns and beams as well as temporary
post and shoring planks having a minimum bearing of 60mm on the structural
supports and on temporary planks having a minimum bearing of 100 mm. The
shoring planks shall be placed perpendicular to long edges with one plank
on each end of the board and one at the centre.Thus all the planks are at
600mm centres. The props shall be at 1200mm centres. The props should be
adequately secured to ensure no buckling takes place till the concrete is
hardened and the temporary props and planks are removed. Fixing Connecting Clips - the StrandecTM Slab planks are fixed with connecting plank clips on both the longitudinal edges at both the end junctions and one at the centre such that the spacing between the clips is a maximum of 600mm. Rebar placement - rebaring is to be done as specified by the structural engineer. Mesh - Anti-crack mesh should be placed as specified by the structural engineer. Concrete Placement - The conventional practices in concrete placement shall be carried out as per structural engineers specifications. Removing Temporary props and planks - After the concrete has set to the required strength, the temporary props and planks are removed as per standard procedures. |
|||||||
![]() |
|||||||